home      project description      project alternatives      legal framework      public participation
environmental & social impacts      lessons learned
Q & A      references      links
Power Point Presentation


Results

 

Alternatives to the Project

 

The result of the screening process identified Nuclear Power generation as the optimal choice for the project. It was acknowledged as being able to meet, with the potential to exceed, the demand for energy in the province of Ontario in a manner that is consistent with the IPSP (OntarioÕs Integrated Power System Plan).

 

The Refurbishment of existing units at the Bruce B site was not viewed as a suitable alternative to the project for the reasons below:

 

(1) The 25 to 30 year life of a refurbished Bruce B station is less than half of the 60-year life of the Project. Accordingly refurbishment of Bruce B does not meet the timeline of the Project.

 

(2) Refurbishment of Bruce B would occur over approximately six years. Beginning in 2016, the electricity generating capacity of the Bruce Power site would be reduced by at least 800 MW as each of the four Bruce B units are taken off-line. In contrast, the Project could make up for this reduction in electricity generating capacity and maintain the site output at 6,300 MW through substituting for the Bruce B units as they come off-line starting in 2016.

 

 

(3) Costs of refurbishing reactors are similar to the construction cost for new reactors. The estimated cost of refurbishing CANDU units runs from $2,100 to $2,800 per kilowatt of installed capacity [1463, 1467, 1466]. This is similar to the capital cost assumed for new reactors ($2,868 per kilowatt of installed capacity), although new units would operate for at least twice the time period.

 

 

(4) The electricity generating capacity of the refurbished Bruce B station is approximately 3,200 MW. This limits the total electricity generating capacity of the Bruce Power site to 6,300 MW and removes the opportunity to increase the output from the site in the event that additional base load electricity is required at some time in the future.

 

(Bruce, 2008a)

 

Alternative Means of carrying out the Project

 

The Alternative project Scenarios are selected as follows:

 

Alternative Project Scenario 1 – Air-insulated Switchyard

Alternative Project Scenario 1 differs from the Reference Project only by including the use of air insulated switchyard technology. Air-insulated switchyards have a relatively large footprint since open air is providing the insulating medium. This widely used switchyard technology is currently the standard design in Ontario and is in operation at Bruce A and Bruce B.

 

Alternative Project Scenario 2 – Dry Storage Facility

Alternative Project Scenario 2 assumes that there will be an interim period of dry storage for used fuel prior to transferring used fuel to the national long-term management facility operated by the NWMO. In this case, dry storage of used fuel will be either located at the WWMF, or additional capacity will be constructed and operated on the Bruce Power site for either CANDU fuel bundles, or the larger light water reactor fuel assemblies.

 

Alternative Project Scenario 3 – Low and Intermediate-level Waste Facility

This alternative will involve construction and operation of a dedicated waste management building for the ProjectÕs low and intermediate-level waste. Alternative Project Scenario 3 will be implemented if it is not possible to store low and intermediate-level waste at the existing WWMF at the Bruce Power site.

 

Alternative Project Scenario 4 – Site B

Alternative Project Scenario 4 involves the siting of the Project at Site B. Site B is located adjacent to Bruce B, on lands partially occupied by office buildings (Figure 4.8.2-1). This Alternative Project Scenario will involve works and activities that are largely bounded by the Reference Project. The Project will involve the same condenser cooling system, switchyard design and radioactive waste management

systems that comprise the Reference Project.

 

Alternative Project Scenario 5 – Site C with Mechanical Draft Cooling Towers

Alternative Project Scenario 5 involves the construction and operation of mechanical draft cooling towers for the cooling needs of the plant, as described in Section 5.4.2.5. Mechanically driven fans that are powered by the power plant will dissipate heat to the atmosphere in place of once-through cooling. This alternative is located at Site C due to the additional area necessary to site the cooling towers adjacent to

the power block (Figure 4.8.2-1). Although cooling towers require make-up water and discharge some heat to the lake with blowdown, this Alternative Project Scenario will greatly reduce the heat load to Lake Huron in comparison with the use of a once-through cooling system. Cooling tower systems will require a relatively larger land area to provide the cooling capacity for the Project.

 

Alternative Project Scenario 6 – Site D with Once-through Cooling

Alternative Project Scenario 6 involves the siting of the Project at Site D (Figure 4.8.2-1). Site D is located on the site of the former Bruce heavy water plant, which is currently in the final stages of decommissioning activities. This Alternative Project Scenario will involve works and activities that are largely bounded by the Reference Project. The Project will involve the same condenser cooling system, switchyard design, and radioactive waste management systems that comprise the Reference Project.

 

(Bruce, 2008a)

 

The chosen alternative means for the reference project and their characteristics are as follows:

 

-        Reactor Design Bounding Plant Envelope

-        Situated on Site A

-        Once through cooling strategy

-        Switchyard design – Indoor SF6, synchronizing breakers and SF6 circuit breakers

-        On-site storage of used fuel by extended wet storage in the reactor used fuels bays

 

Figure A3 portrays the characteristics of
the selected Reference Project.

Figure A3

The results of the comparison of alternatives (see Table A4
above) revealed that alternative scenario 4 and 6 scored the
highest, with scenario 6 ranking the highest out of all scenarios.