home      project description      project alternatives      legal framework      public participation
environmental & social impacts      lessons learned
Q & A      references      links
Power Point Presentation

page1    page2    page3   

Assessment of Aboriginal issues

 

Methodology

 

The assessment of issues of importance to Aboriginal communities was done by:

-       Describing the existing environmental conditions focusing on the issues of importance;

-       Prediction and assessment of the likely effects of the Reference Project including the identification of plausible interactions and measurable changes;

-       Identification of the likely effects of the Project;

-       Consideration of opportunities to mitigate the effects and identification of effects that remain following proposed mitigation (i.e. residual effects);

-       Prediction and assessment of likely effects as a result of the Alternative Project Scenarios following the method used for the Reference Project;

-       Evaluation of the significance of all residual adverse effects and

-       Identification of follow-up monitoring programs to ensure that effects are as predicted.

 

Most issues were determined to have no measurable change or residual adverse affects. However, two issues regarding First Nations were furthered for further assessment:

First Nation Issues furthered for assessment

Bruce Power Assessment

No measurable change in health is likely since the SON reserves are located outside the area in which the air quality, traffic degradation and health care effects are expected. Although no residual adverse effects are identified from a radiological perspective, a potential interaction during the Operations Phase was advanced for further assessment since a radiation dose of any magnitude is a concern to members of the First Nations communities.

The highest dose to the Saugeen First Nation community, the closest First Nation community to the Bruce Power site, from the Reference Project will be 0.7% of the regulatory dose limit of 1000uSv/yr. This is considered negligible.

A measurable change to economic viability (tourism) is likely due to the decrease in the availability of tourism accommodation during the Construction Phase. The decrease in availability could bring increased revenue to the First Nations as a result of increased tourism demand (this impact was not noted in the section on Aboriginal interests).

The Saugeen First Nation is located in a high-demand tourism area with 6,000-8,000 annual visitors and 1,250 rental or leased cottages.  It is likely that, in the event of increased demand for tourist accommodation, the Saugeen First Nation cottage industry could operate at an increased capacity, which in turn would generate increased revenue for the community. This is a likely beneficial effect.

 

Issues that will need assessment if Bruce Power proceeds with the Project:

-       The Construction Phase could result in the physical alteration of the areas encompassed by the First Nations' land claim to their traditional territories. The First Nations claim of Aboriginal title to their traditional territories under the waters of Lake Huron and Georgian Bay could be affected by infilling of MacPherson Bay, construction of the cofferdam and construction of the intake and discharge tunnels.

-       The SON has also launched a claim for Aboriginal title to their traditional territories under the waters of Lake Huron and Georgian Bay. The area of disturbance to the lake bed as a result of the Construction Phase is approx 0.55ha for the intake and discharge tunnels and 8.3ha for the infilling of MacPherson Bay. This area is small relative to the full area of the claim and the modification to the lake bed will not affect the validity of the claim. This issue requires discussion between the First Nations and Bruce Power if Bruce Power makes the decision to proceed with the Project.

 

Mitigation

There are no likely adverse affects identified on either First Nations or MŽtis communities as a result of the Reference Project or Alternative Projects - no alternative is assessed as being preferable to the Reference Project with regards to Aboriginal interests. Therefore Bruce Power has determined that no additional mitigation measures beyond those inherent within the Project design are identified. As well, no likely residual adverse effects to Aboriginal Interests are identified as a result of the normal operation of the Project. There are no likely adverse effects on the sustainability of the renewable surface water resource or the fisheries resource as a result of the Reference Project and each of the Alternative Project Scenarios. Overall, there are no likely adverse effects on the renewable resources used by First Nations or MŽtis in their respective traditional territories and no further assessment is required.

However, considering the importance of the First Nation fishery to their livelihood, further studies on Lake Whitefish should have been conducted (see section on weaknesses).

 

Follow-up

The final follow-up program will be developed through peer and public review as well as discussions with the following groups, at a minimum:

-       The CNSC, DFO and other federal regulatory agencies;

-       Provincial regulatory agencies including the MOE and MNR;

-       The Municipality of Kincardine;

-       Community organizations such as the Lake Huron Fishing Club, Saugeen Field Naturalists and the Lake Huron Centre for Coastal Conservation; and

-       Members of the Saugeen Ojibway Nations and the Saguingue MŽtis Council.

 

The methods to consult on the follow-up program will be similar to those used throughout the EA process and will include, at a minimum, the following:

-       Notification of stakeholders;

-       Workshops;

-       Posting of information on Bruce PowerÕs website; and

-       Documentation of comments and how they are addressed.

 

Since no significant adverse effects to aquatic biota (specifically Lake Whitefish larvae) there will be a continuation of on-going studies to determine extent of use of spawning shoals with no additional monitoring is required during the construction phase. During the operations phase it is simply recommended to quantify the presence of whitefish in the vicinity of the Bruce Power site.

 

The Responsible Authorities (CNSC, DFO and Transport Canada) have the overall responsibility to ensure that appropriate mitigation measures are implemented and the follow-up monitoring is designed and carried out.

 

Weaknesses

There are currently no active MŽtis land claims in Bruce or Grey Counties; however, these issues are not thoroughly discussed in the EIS as Bruce Power simply states that these are issues that will require further discussion if Bruce Power makes the decision to proceed with the project.

As well, the EIS doesnÕt mention the population of the two reserves. Only says that they are 1.9% of the population of the Regional Study Area is Aboriginal.

 

Aboriginal traditional Knowledge may be obtained through the review of published information and through dialogue with Aboriginal communities. In section 2.6.2.1 the literature review of four documents containing SON traditional knowledge is described. However, there is clearly a problem with the obtainment of tradition knowledge through dialogue. A traditional knowledge questionnaire was drafted for use in mid-2007 and was submitted to the SON for review. This questionnaire was supposed to be distributed to community events during August 2008 but it is not clear what happened with this questionnaire, if it was ever distributed or if it was incorporated into the EIS.

As well, interviews with the Saugeen First Nation program directors were conducted but the directors were unable to provide traditional knowledge themselves and referred the EIS consultants to a community traditionalist. It is stated in the EIS that attempts were made to obtain interviews with the program directors of the Chippewas of Nawash Unceded First Nation but could not be conducted within the timeframe of the EIS. An interview with a traditionalist on the Saugeen First Nation reserve was discussed with the band administration; however, a consensus on the scope of the interview could not be reached within the timeframe of the EIS.

The Review Panel submitted a request for information regarding Aboriginal Issues. They stated that Òaccording to Table 14.2.4-1 the effect of increased temperature on Lake Whitefish spawning and recruitment will be a minor residual adverse effect. Given the likely importance of this topic to First Nations interests, further information is requested in Section 15 (preliminary follow-up monitoring program) on how this finding will be addressed relative to past efforts on the same topic. Bruce Power has an existing EMS for Lake Whitefish that was implemented in 2003 (Chippewas of Nawash website, 2007). They could simply include this monitoring program in the EIS with added measures for the construction phase.

 

In the EIS Bruce Power provides a summary of pre-submission AND a summary of post-submission SON involvement methods and outcomes with a list of activities, the dates, the topics and documents discussed and principal outcomes. However, with regards to the MŽtis, there is only one summary providing this information for both pre- and post-submission involvement methods and outcomes. Clearly there was much less dialogue with the MŽtis than with the First Nations groups.

Most VECÕs suggested at workshops and public reviews are not included in the EIS as they were not considered good indicators or there were other indicators that were very similar. However, due to public complaint Round Lakefish was requested by the review panel to be incorporated

Another possible weakness is the lack of consultation with American stakeholders. This Project is near the border with Michigan and could involve trans-boundary issues. Bruce Power mentions sending information to American NGOs but never mentions if or how they participated.

 

Strengths

Overall the EIS compliance with the Terms of Reference is good; as well, the methodology and types of consultation used to gather information were thorough and clearly stated in the EA report as well as the results of the consultation regarding the questions and concerns of local communities. Bruce Power clearly understands the importance of community support with regards to nuclear projects.

Bruce Power has an overall good relationship with the local Aboriginal communities. Objectives for involvement of First Nations were developed through discussion between the SON Chiefs, Chief Nadijwan and Chief Kahgee, and the Bruce Power President and CEO, Duncan Hawthorne, in December 2006. These objectives include:

-       Inform SON leaders and their communities about the Project, in a timely and on-going manner, as appropriate;

-       Develop an understanding of the SON, their communities and traditional knowledge and how they might potentially be affected by the Project;

-       Provide support to the SON to encourage their meaningful participation in the environmental assessment;

-       Consider and respond to the SON«s concerns and issues relating to the Project;

-       Facilitate SON review and discussion on the EIS and supporting technical studies.

 

In September 2007, the SON hired an EA co-ordinator, funded by Bruce Power, with independent reporting to the SON Environmental Office. The funding provided by Bruce Power is also intended to supplement the funding made available to SON through the CEAA«s participant funding program. Bruce Power also agreed to provide capacity funding to the Saguingue MŽtis Council to facilitate their involvement.

 

A Protocol Agreement was signed on May 23, 2008 at the Administration Office of the Saugeen First Nation. This agreement outlines the working arrangements between SON and Bruce Power throughout the balance of the EA process. This agreement also enables additional capacity funding to be provided retroactively to the SON for activities since the beginning of the process.

 

Bruce Power has been collaborating for the last five years with the SON on research regarding aquatic environment supporting the Aboriginal commercial fishery which harvested Lake Whitefish in the eastern main basin of Lake Huron. Bruce Power has also maintained good relations with the MŽtis since its 2001 inception and sponsored the formation of the MNO Chartered Community Council in 2002. The Saguingue MŽtis Council also participated in the collaborative research on the lake whitefish fishery.

 

Since Bruce PowerÕs inception in 2001 they have maintained good community relations and Duncan Hawthorne, the CEO, has even been called the ÔKind of KincardineÕ by the local media.

 

Consultation with DFO biologists relating to the possible infilling of MacPherson Bay led to the identification of three alternative approaches and the selection of the alternative requiring the least infill. This consultation resulted in an 80% reduction of the area to be infilled compared with Bruce Power«s original proposal.

 

 

 

Comparison with Hydro QuebecÕs Gentilly-2 Nuclear Generating Station

 

Hydro QuebecÕs Gentilly-2 nuclear power station is located near Becancour, Quebec. The main difference: between the Bruce Power nuclear station and Gentilly-2 is that Gentilly-2 is smaller with only one operating reactor. Hydro-Quebec submitted an EIS in February of 2006 regarding refurbishment of the reactor in order to extend its life from 2007 to 2040. Eventhough the proposal is of a much smaller scale than the Bruce Power project both projects encountered the same issues.

 

Unlike the Bruce Power EIS, in the Gentilly-2 EIS, Hydro Quebec gives has a section entitled Portrait gŽnŽral des communications sur Gentilly-2 where it gives a summary of public engagement methods and activities since commissioning in 1974. This would have been beneficial in the Bruce Power EIS as it presents a big-picture of overall public engagement and puts into context the relationship between the Project and the Public. Bruce Power has a section entitled Community Relations since their inception in 2001 but they donÕt describe the public engagement methods, only the funding they have provided to First Nation projects. However, Hydro Quebec does not describe their previous relationship with the local Aboriginal group.

 

Both groups held workshops regarding VECs. Bruce Power only incorporated two publicly suggested VECs but Hydro Quebec makes no mention of any of their VECs coming from public consultation. Therefore in this regard Bruce Power was more successful in engaging the public; perhaps the methodology they used was better developed than that of Hydro Quebec or perhaps they were clearer in communicating the requirements for selecting VECs. 

 

Both companies respect and carefully abide by the regulatory requirements regarding public engagement.

 

With regards to distribution of information and public consultation Hydro Quebec and Bruce Power used very similar methods. The methods employed by Hydro Quebec are:

-       Analysis of environmental reports on Gentilly-2 from 1993 to 2001;

-       Analysis of public polls on health and safety risks from 1986, 1991, 1993 as well as new polls in May and June of 2003 regarding refurbishment and perceptions of risk;

-       Public opinion surveys – the survey was administered by telephone to a sample

of 800 adults distributed in different regions of the province. Results were analyzed: approval rating was generally between 65 and 70% from 2003 to 2005;

-       Group discussions - Six interviews with discussion groups made up of 12 interested people from the public;

-       Two workshops regarding VECs were held in 2002. Results were reconfirmed in 2003 during public consultations;

-       Development of a consultation programme began in 2003;

-       Newsletters– distributed to 1600 people;

-       Information telephone line;

-       Hydro-Quebec welcome office;

-       Email;

-       Internet site for the project;

-       Information column published in a number of regional weekly newspapers from 2003-2005;

-       Analysis of published articles on Genilly-2 in the press  (the analysis showed an approval rating of 67 to 79% during 2002 to 2004);

-       Articles published in magazines regarding various subjects concerning Gentilly-2 (propaganda);

-       Public notices in newspapers regarding information events, public hearings and open houses;

-       Invitations for information events and open houses were sent to all residents of surrounding municipalities – 68,500 homes;

-       Documentation posted by Hydro-QuŽbec in response to requests for information;

-       Information Kiosks in local towns and municipalities;

-       Videos regarding Gentilly-2 are available to the public;

-       Open-houses;

-       Media relations – press releases, press conferences, interviews with journalists;

-       Individual meetings with mayors, deputies and Aboriginal leaders;

-       Meetings with target organizations;

-       Information events and public consultations;

-       Questionnaires were distributed at the public information meetings and analyzed in 2003;

-       Hydro Quebec participated in a nuclear debate was held on October 9th, 2003, organized by a college in Trois-Rivires; the aim was to permit the exchange of information and education;

-       Le Plan des mesures dÕurgence nuclŽaire externe (PMUNE) was incorporated into the public consultation plan;

-       Meetings of members of the Table of Information Exchange (TIE) – comprised of 9 members from regional organizations including the First Nation Community of Wolinak. However, Aboriginal members pulled out of these meetings following their opposition to the project in 2003. The other members included two representatives from the town of Becancour and the municipality of BŽcancour, one representatieve each from the Conseil rŽgional de lÕenvironnement du Centre-du-QuŽbec (CRECQ), the Chambre de commerce de BŽcancour, the Centre local de dŽveloppement (CLD) de BŽcancour,  the ConfŽrence rŽgionale des Žlus du Centre-du-QuŽbec (CRƒ, rŽgion 17), the ConfŽrence rŽgionale des Žlus de la Mauricie (CRƒ, rŽgion 04) and the SociŽtŽ du parc industriel et portuaire de BŽcancour.

 

This Table of Information Exchange was an important part of their consultation process. In 2004, the members of the TIE held two meetings where Hydro-QuŽbec resented a summary of the impact study conducted in January of 2004 and a summary of the study conducted on the Projects economic impacts on the region.

 

Hydro Quebec is much more detailed in describing its methodology and includes several forms of engagement not used by Bruce Power such as analysis of local media coverage, publishing a weekly information column in local newspapers and participation in a debate with the theme of La central nuclŽaire de Gentilly doit-elle tre rŽnovŽe ou fermŽe? As well, the organization of a ÔTable of Information ExchangeÕ was an interesting way to approach group discussion.

 

Another difference was that Hydro Quebec ordered the results of the public consultation into 8 themes and addressed them accordingly in the EIS. This is perhaps a better method than the one used by Bruce Power who addressed the top 10 questions in the body of the EIS, as the themes cover more ground giving a better overall view of concerns and we can always go to the Appendix to see the specific questions.

 

The question themes for Gentilly-2 are:

-       Environment and health;

-       Social impacts;

-       Management of radioactive waste and storage;

-       Emergency plans and the security of storage of waste;

-       Decommissioning and dismantlement of Gentilly-2;

-       Electric shocks;

-       Economic impacts;

-       Nuclear energy in Canada and around the world

 

Bruce Power has better relations with the local Aboriginal groups compared to Hydro Quebec. Bruce was successful in signing a protocol agreement with both the SON and the MŽtis. More involved with Aboriginal groups through sponsorship of activities and events, development of Native Circle at plant, collaborative research on Lake Huron Lake Whitefish fishery. On the other hand, Hydro Quebec was not successful in engaging the local Aboriginal group, Wolinak. Following several meetings between the band council and Hydro Quebec representatives in 2003 the band submitted a letter of opposition against the project. The band council declined all invitations to participate in meetings in 2004 and 2005. Hydro Quebec was met with a demonstration against the project in September of 2005.

 

 

Lessons Learned

 

Public consultation is not just a means to gain support but can be very effective in providing the proponent with useful information. For example, public consultation resulted in new VECs and in finding an alternative for the infilling of MacPherson Bay which resulted in an 80% reduction in the area to be infilled.

 

The obtainment of Traditional Knowledge can be very complicated. Aboriginal communities are often not willing to provide this information if they do not think it will be beneficial for them to do so. The gathering of this information requires great sensitivity and patience on the part of the proponent.

 

 

Videos

 

Life at Bruce Power
(http://www.youtube.com/watch?v=j05R-nJxEsM)





Citizens for Bruce C
(http://www.youtube.com/watch?v=W61JHQa9OMs)


 

 

References

 

Major Projects Management Office, Government of Canada: Early Aboriginal Engagement: A Guide for Proponents of Major Resource Projects. Retrieved March 15, 2009 from http://www.mpmo-bggp.gc.ca/desc/aboriginal-autochtones-eng.php

 

Department of Justice: Canadian Environmental Assessment Act. Retrieved March 15, 2009 from http://laws.justice.gc.ca/en/C-15.2/

 

UNEP: Environmental Impact Assessment Training Resource Manual, 2nd Edition. Topic 9: Review of EIA Quality. http://www.unep.ch/etu/publications/EIA_2ed/EIA_E_top9_tit.PDF

 

Nuclear Energy Agency Organisation For Economic Co-operation and Development: Society and Nuclear Energy: Towards a Better Understanding: Retrieved April 6, 2009 from: http://www.nea.fr/html/ndd/reports/2002/nea3677-society.pdf

 

Kleinu, S., coordinator for Citizens for Renewable Energy (2009, Jan 8). Round Whitefish and VECs. [Email to program funding officer]. Canadian Environmental Assessment Agency.

 

Chippewas of Nawash website. (2007). Retrieved April 5, 2009 from: http://www.nawash.ca/index.shtml