![]() |
environmental & social impacts lessons learned Q & A references links Power Point Presentation |
Methodology
Alternatives to the Project
There were 7 alternate electricity-generating options, which includes nuclear generation,
that were discussed in the EIS as possible alternative forms of meeting or exceeding the
demand for energy in the province of Ontario. These are congruent with the Ontario Power AuthorityÕs
(OPA) recommendations for the current energy supply mix for Ontario. These are
outlined in table A1. A small section was given to describe each, as well as
their respective characteristics. (Section 4.4-4.7)
A selection process was used to uncover the best
possible electricity generating option. This included a screening process
against 5 selection criteria that were based on technical and economic
feasibility. The selection criteria are described below. The overall process is
shown in Table A2.
An electricity-generating
alternative should be capable of meeting all of the following five selection
criteria to be considered as economically and technically feasible:
¥ Capable
of generating a minimum of 3,300 MW of baseload electricity: Dependability and reliability of
baseload electricity generation capacity is essential to the operation of the
provincial electricity network. A particular alternative must be of sufficient
size and be capable of generating its design electrical capacity reliability
throughout the year;
¥ Capable
of being sited at the Bruce Power site: Approximately 200-300 ha of land on the existing Bruce
Power site are undeveloped and could be used for siting a new power plant. A
particular alternative must be capable of being constructed and operated within
this footprint;
¥ Available
commercially: The
IPSP requires that additional electricity generating capacity is available
beginning in 2016. An alternative must be capable of connection to the
provincial grid within this timeframe. This requirement eliminates any unproven
and untested technologies;
¥ Cost-effective:
The estimated
life cycle cost of electricity generated by the alternative should be
comparable with the current cost of electricity generation (approximately 5
cents per kWh). In addition, an alternative should have a relatively stable
cost for fuel because of baseload generation requirements; and
¥ Consistent
with the requirements of the IPSP: The Ontario government has decided upon the conservation
and limit on growth demand that might be expected, the supply mix (i.e., the
relative proportion of each generating technology) and the technology type
(e.g., the phase out of coalfired power generation in the province as quickly
as possible). A particular alternative must satisfy the requirements of the
IPSP.
Table A
An
additional alternative was also discussed. This was the Refurbishment of
existing units at the Bruce B site.
The Bruce
B station consists of:
-
Four
units with a total electricity generating capacity of approximately 3,200 MW
-
Units
brought into service between 1984 and 1987
-
Require
mid-life servicing to extend their operating life
-
Bruce
PowerÕs current estimate for refurbishment is between 2016 and 2022
-
Once
refurbished, reactors should be capable of an additional 25 years of operating
life
-
Predicted
to be capable of generating approximately 3,200 MW through approximately 2044
-
An
environmental assessment of the operation of the Bruce B through 2044 was
completed in 2005
Alternative Means of
carrying out the Project:
The methodology
that was used to determine the alternative means of the project is never
mentioned throughout the EIS. The different means are only identified by Bruce
Power with no background information of the selection process. The 5
alternative means that were identified are the following:
-
Four
state-of-the-art nuclear power reactors of Canadian and international design
-
Four
alternative site locations on the Bruce Power site (932 ha)
-
Two
cooling water strategies, involving air and water cooling
-
Two
switchyard designs comprising alternative technologies
-
On-site
and off-site radioactive waste management strategies
Below are some examples of the
alternative means – the four nuclear power reactors considered (Figure
A1) and the four alternative site locations considered (Figure A2)
Figure A2
A reference project was then
chosen from a conglomerate of the preferred alternative means. As well, 6
project scenarios were given that involve variations of the reference project
and different alternative means. For example alternative project scenario 4 is
the same as the reference project except it is situated on site B (instead of
site A which was chosen for the reference project) and it is using the
once-through cooling system.
A methodology was used to help in
the selection of the appropriate alternative means. This consisted of comparing
the residual adverse effects for each component of the environment that was
assessed for significance throughout the project, and identifying the relative
benefits and detriments of each of the alternative project scenarios compared
with the reference project. An example of how this was completed is shown in
Table A3.
Table
A3
A summary of the comparisons of alternatives conducted for
all environmental components was given and is shown in Table A4.
Table
A4