![]() |
environmental & social impacts lessons learned Q & A references links Power Point Presentation |
Compliance of EIS with Terms of
Reference:
Table A5 and Table A6 reviews the
proponentÕs compliance with the EIS guidelines that were outlined by the joint
panel review. The first column indicates the guideline and its section, the
second column states if the guideline was answered or not, and the third
indicates the corresponding section of the EIS. The asterix indicates that the
criteria was addressed but involved flaws or was missing certain parts.
Table
A5
Table
A6
Other
Relevant documents pertaining to alternative requirements in EISÕs:
UNEP EIA Training Manual – Review of EIA Quality
The UNEP
Training Manual for EIA review states that when taking into account the
consideration of alternatives the following should be included in order to
allow for a strong EIA:
-
The
consideration of reasonable alternatives
-
A
comparison between the different alternatives
EIA Center – University of Manchester
paper: ÒReviewing the Quality of Environmental StatementsÓ
An
occasional paper from the EIA Center at the University of Manchester titled
– ÒReviewing the Quality of Environmental StatementsÓ, by Lee N and
Colley R (1992) outlines relevant areas of consideration with regards to
alternatives:
-
Feasible
alternatives to the proposed project should have been considered. These
should
be outlined in the Statement, the environmental implications of each presented,
and the reasons for their rejection briefly discussed, particularly where the
preferred project is likely to have significant, adverse environmental impacts.
-
Alternative
sites should have been considered where these are practicable
and
available to the developer. The main environmental advantages and
disadvantages
of these should be discussed and the reasons for the final
choice
given.
- Where available, alternative
processes, designs and operating conditions
should
have been considered at an early stage of project planning and the
environmental
implications of these investigated and reported where the
proposed
project is likely to have significantly adverse environmental
impacts.
Compliance
of Alternatives to the Project to EIS guidelines and Overall Strengths and
Weaknesses:
Strengths:
This section addressed all of the
issues outlined in the guidelines that were provided by the joint panel review.
The overall quality and
performance was well done – fairly easy to read and comprehend.
Weaknesses / Omissions:
Following the guidelines that were
outlined by the joint review panel seemed almost religiously done and left no
outside room for additional thought with regards to the topic at hand.
Only addressed the criteria
outlined in the Terms of Reference and did not seem to take the question of
alternatives to the project seriously.
Regarding criteria 4 in the terms
of reference, the guidelines state that - Òthe EIS must explain how the proponent developed the
criteria to identify the major environmental, economic and technical costs and
benefits of the alternatives, and how the proponent identified the preferred
project based on the relative consideration of the environmental, economic and
technical benefits and costs.Ó – however there is barely any discussion
about the environmental cost and benefits throughout the text – and the
main focus is solely on the economic and technical feasibility. This is further
proven by the specific exclusion of the environment in the design of the 5
selection criteria that was used in the screening process to determine the most
appropriate alternative.
Related to this, it was found that
the screening selection criteria were very limiting, leaving little room for
any real viable alternative projects to be considered. For example one of the
criteria states that the alternative project must be capable of being sited at
the Bruce Power site on approximately 200-300 ha of land. This places a very
narrow scope with regards to the consideration of alternatives.
Compliance
of Alternative Means to EIS guidelines and Overall Strengths and Weaknesses:
Strengths:
This section followed the Terms of Reference well –
giving descriptions in all the right places and attempting to make certain all
guidelines were adhered to.
Addressed all but one of the issues outlined in the
guidelines that were provided by the joint panel review.
The overall quality and performance was well done; the
methodology used was easy to follow and make sense of - allowing the material
to be understood by a larger audience.
The section makes many references to Bruce Powers
compliance with IPSP and OPA standards for energy and their strong partnership
with the Ontario government in regards to its energy policy.
Weaknesses / Omissions
Major
omissions were discovered that hinted towards the lack of serious thought being
given to this section.
The main
EIS assesses 6 project scenarios throughout the document, however the technical
support documents, which are intended to go into more detailed information,
only look at 5. Project scenario 6, which incorporates alternative site D and
is the final site alternative is not assessed among all the TSD. This omission
was also found by the joint review panel and the correction of this missing
information has been requested on March 11th of this year. It is
very confusing as to why the proponent would leave out all this pertinent
information – and especially because alternative project scenario 6
ranked the highest out of all scenarios in the comparison assessment that was
stated before (see Table A4 ÒSummary of Comparison of AlternativesÓ).
Both
alternative scenarios 4 and 6 ranked higher than the reference project during
the comparison of alternatives. It is stated in the document that –
Òbased on these results there are some benefits to locating the Project at
either Site B or Site D.Ó Seeing as how all the environmental studies completed
in the EIS are based upon the reference project, it is a little misleading as
to why so much focus resided with this option and not with the higher-ranking
alternative scenarios.
An
omission that is evident has to do with missing information regarding one of
the guidelines outlined in the terms of reference. It is stated, Òthe EIS must
describe the environmental effects of each alternative meansÓ – this was
not completed for the alternative means that were identified at the beginning
but were not used in the reference project and the project scenarios. This
brings up questions of uncertainty because if there were no environmental
assessment completed for these missing alternative means in what capacity were
they deemed unworthy? – There is no explanation for this in the text.
It is difficult to keep track of
different Alternative Project Scenarios (APSs) and their respective components.
For example Alternative Project Scenario #1 is the Air Insulated Switchyard.
However, throughout the rest of the document it is only referred to as APS #1,
thus causing difficulty for the reader to immediately recognize which APS the
text is referring to, especially when there is a discussion concerning multiple
APSs. This aspect was also found by the joint review panel and the proper
adjustments have been requested.
UNEP EIA Training Manual – Review of EIA Quality
The
rating scale for EIA Review that is provided within the UNEP training manual
for EIA Quality is shown below in Table A7. With consideration of all the
components of this section relating to Alternatives and Alternative Means to
carrying out the project – A grade of B is awarded.
Table
A7
Rating
Scale for EIA Review:
Rating |
Explanation
|
A |
generally
well performed, no important tasks left incomplete |
B |
generally
satisfactory and complete, only minor omissions and inadequacies |
C |
just
satisfactory despite omissions and/or inadequacies |
D |
parts
well attempted but must, on the whole be considered just unsatisfactory
because of omissions and/or inadequacies |
E |
unsatisfactory,
significant omissions or inadequacies |
F |
very
unsatisfactory, important task(s) poorly done or not attempted |
N/A |
not
applicable, the review topic is not applicable in the context of the project |